We’re building a community.

Exciting progress is happening at our newest project site! Here’s a look at what’s underway:

  • Home #1 – Framing is nearly complete, with roof trusses for the house and garage now in place. Rough electrical and plumbing are moving forward, and we’ve begun installing windows and house wrap. Scaffolding is up, making it possible to tackle work at higher levels.
  • Home #2 (3-Bedroom) – The first-floor exterior walls are up, interior walls are underway, and the garage framing will follow soon.
  • Home #3 (2-Bedroom) – Foundation trenching and concrete forms are set. Next steps include in-slab plumbing and electrical, then concrete footings, gravel, and rebar.
  • Site Work – Our pre-construction meeting with PG&E and C&D went smoothly. Crews will soon return to complete underground electrical, water service lines, cable installation, and final grading.
  • Volunteers – We were thrilled to welcome a new volunteer, Alex, to the team, and to see future homeowners join us on site! We also hosted students from the Sierra College Construction Program for a site tour, giving them a firsthand look at affordable housing in action.